For over 30 years, METR has been implementing successful state strategic contracts for the decommissioning of nuclear facilities, with a primary focus on technologies for the processing and disposal of radioactive waste (RW) of varying activity levels.
All of the company's contractual obligations are being fulfilled in full.

METR leads consortiums that, at various times, have included partners such institutes and design organizations as
JSC GI, VNIPIET, FSUE Radon,
JSC Alliance-Gamma, RAOTEKH, and JSC Malaya Energetika.



Standard solutions for decommissioning nuclear facilities
As shareholders of Malaya Energetika OJSC from 2001 to 2005, under a contract with Rosenergoatom, METR managed the development of the Small Floating Nuclear Power Plant (PATES). The project successfully passed the State Expert Review and was handed over to the Client.
Currently, the floating nuclear power plant "Akademik Lomonosov" is serving in the port of Pevek, Russia.
  • 2026-2022

    Scientific research and development of regulatory documents for assessing the radiation situation during beyond-design-basis radiation accidents at the design stage. Development of regulatory requirements for the protection of particularly hazardous facilities (NPPs) from unmanned aerial vehicles (UAVs).

  • 2022-2018

    Client: MAEK-Kazatomprom LLC


    Development and presentation of a feasibility study at the State Expertise State Enterprise (Gosekspertiza)

    "Decommissioning of the BN-350 reactor facility."

  • 2017-2016

    Client: Rosenergoatom Concern, a subsidiary of Rosenergoatom Concern


    Support and technical support for permitting activities during the design and licensing of Unit No. 4 of the Beloyarsk NPP with a BN-800 reactor plant.


    Client: Leningrad Nuclear Power Plant, a subsidiary of Rosenergoatom Concern


    Development of working documentation and cost estimates for organizing additional sorting by specific activity of solid radioactive waste after compaction in Building 672R.

  • 2015

    Client: Moscow Department of Science and Industrial Policy


    Development of environmentally friendly and biologically inert X-ray-protected materials and products to ensure the safety of medical and emergency rescue personnel.


    Client: IPPE State Research Center of the Russian Federation


    Calculation of the volume of conditioned radioactive waste after reprocessing

    of spent nuclear fuel from the BN-1200 reactor.


    Client: VNIPIET JSC, St. Petersburg


    Preparation of materials for the development of design and engineering documentation for the first stage of construction of the MBIR nuclear research facility, covering radioactive waste management and decontamination.

  • 2012-2011

    Client: MAEK-Kazatomprom LLP


    • Development of technical specifications and designs for process units and non-standardized equipment for the 1st and 2nd launch complexes of the liquid radioactive waste processing facility.

    • Development of a working design for a liquid oil-containing radioactive waste processing facility.

    • Development of a design for the management of high-level waste from the BN-350 reactor plant.

    • Development of working documentation for the 1st and 2nd launch complexes of the liquid radioactive waste processing facility for the first year of construction and storage (for 50 years).

  • 2010-2009

    Client: MAEK-Kazatomprom LLC


    Development of a technical design for a liquid oil-containing radioactive waste processing facility.


    Client: MAEK-Kazatomprom LLC


    Development of a design for a sanitary protection zone and observation zone for the decommissioning of the BN-350 reactor plant.

  • 2008

    Client: MAEK-Kazatomprom LLC


    • Development of a technology for processing liquid oil-containing radioactive waste.

    • Research and development to determine the conditions for decontaminating the equipment and building structures of the BN-350 reactor facility.

    • Development of a project to prepare the buildings, structures, and utility systems of the BN-350 reactor facility for safe long-term storage (as part of Phase V of construction).

    • Comprehensive engineering survey of the buildings, structures, and utility systems of the BN-350 reactor facility.


    Client: KATEP-AE LLC


    Research of spectrometric measurement methods and development of technical proposals for the composition of a spectrometric system for certifying NZK-type containers containing radioactive waste.

  • 2006

    Client: KATEP-AE LLC


    Analysis of solid radioactive waste management methods and equipment for use in the development of working documentation for the solid radioactive waste management system for the BN-350 reactor plant.


    Client: Institute of Atomic Energy, a subsidiary of the National Nuclear Center of the Republic of Kazakhstan, MEMR RK, Republic of Kazakhstan


    Development of technical proposals for a multipurpose nuclear technology complex

    with a RITM-K reactor plant for the Nuclear Technology Park JSC in Kurchatov.


    Client: KATEP LLC


    Finalization of the liquid radioactive waste management system design for the BN-350 reactor plant, MAEK, Aktau, Republic of Kazakhstan.

  • 2005

    Client: KATEP LLC


    Development of a design for a complex for processing solid low- and intermediate-level waste from the BN-35 reactor.

  • 2003

    Client: National Nuclear Center "Scientific Nuclear Center" of the Republic of Kazakhstan


    Assessment of Nuclear Energy Development Scenarios in the Republic of Kazakhstan.

  • 2003-2004

    Client: MAEK-Kazatomprom LLC - RAOTEKH LLC


    Justification and technical solutions for processing sodium residues after draining the BN-350 reactor circuit. Development of a design for a liquid radioactive waste processing complex.

  • 2002

    Client: KATEP LLC


    Preparation of initial data for the EIA and PRA sections of the BN-350 reactor facility's liquid radioactive waste storage system.


    Client: MAEK-Kazatomprom LLC - KATEP LLC


    Feasibility study for the use of a reinforced concrete cask for storing and transporting spent nuclear fuel from the BN-350 reactor facility.

METR is a member of the Russian Project Management Association SOVNET; its quality management system, covering project management in the field of energy technologies and developments, is certified to meet the requirements of GOST ISO 9001-2011.